Picture log of the construction of my Pagosa Springs home
I designed the house in May and June 2009. The Property Owners permit was sumittted 6/19 and approved 6/30. I waited until the county passed a stimulus and started to give away free building permits to submit mine, 7/8/09. The permit was approved 7/20. Here is a picture chronology of the construction progress.
Back to parent
1 - As I left it for the winter; blends in pretty well, 11/22
2 - Construction shed almost done, 7/2/09
3 - Digging foundation trenches, 7/23/09
4 - Building footer forms, 7/27
5 - Footers ready for concrete (lots of rain slowed me up), 7/30
6 - Finishing footer, 8/1
7 - Block foundation almost done, 8/5
8 - Grouting foundation walls, 8/6
9 - Pouring the slab, 8/17
10 - Finished slab, 8/18
11 - Garage walls go up, 8/19
12 - Lifting main floor meam into position, 8/20
13 - Main floor walls go up, 8/25
14 - Jacking second floor beam into position, 8/26
15 - View out dining room window, 8/28
16 - View out french doors, 8/28
17 - Ridge beam in place, 9/3
18 - Roof deck goes on, 9/12
19 - Roof deck done, need to finish sheathing, 9/19
20 - I was too busy to play golf; had to get it dried in before winter came, 9/26
21 - Brother Marty and Casey work on windows, 10/5
22 - Sheathing on, wrap almost done, 10/11
23 - Siding goes on, 10/14
24 - Metal roofing almost done, 11/5
25 - Not too bad with help of ladders, 11/5
26 - Walking the ridge, 11/5
27 - Just finishing siding, 11/11
28 - Our second snow, 11/15
29 - View from NE, 11/15
30 - View from NW, 11/15
31 - Living room (after dark), 11/22
32 - Interior of main and loft floors, 11/22
33 - As I left it for the winter, 11/22
Back to parent